ISSCT  



INTERNATIONAL SUGARCANE BIOMASS UTILIZATION CONSORTIUM (ISBUC)
Project proposal for ISBUC (No1,June 2007)

 DESIGN, BUILD-UP AND EVALUATION OF A SUGARCANE BIOMASS
(BAGASSE AND TRASH) GASIFICATION PILOT PLANT WITH 3 MWE OF POWER
 

                                                             Project extension: 3 years
1- Abstract

The sugar and alcohol industry is facing enormous changes and fast growth all over the world, mainly related to the massive production of ethanol as a transport fuel. High efficiency electricity production is extremely important in this context, as an additional high value by-product, and also considering the future use of bagasse as a raw material for ethanol production and the possibility of additional revenues through the commercialization of carbon credits.

Gasification technologies could allow the use of gas turbine combined cycles for cogeneration in sugar alcohol mills (the so called BIG/GT technologies – Biomass Integrated Gasification and Gas Turbines) to double the actual electricity generation specific indices. First theoretical proposals were done by Larsson et al. (1987). Bagasse gasification tests at a laboratory scale were carried out at UNICAMP and UNIFEI in Brazil. Pilot plant scale tests were carried out by the Sweden company TPS at its facilities in Sweden in a GEF Project coordinated by COPERSUCAR Technology Center (project "BRA/96/G31 Energy generation out of biomass: sugar cane bagasse and residues").

After this theoretical and experimental research it is necessary to carry-out a small scale industrial implementation of the BIG/GT technology, which is the proposal of this project. 

2- Bibliographic review 

A considerable amount of electricity can be generated by using advanced technologies with a high efficiency of conversion. In this sense the implementation of the integrated technology of gasification and gas turbines (BIG/GT) is very attractive for sugar mills with low steam consumption. The BIG/GT were tested in several demonstration projects in the USA and Europe.

Figure 1 shows a simplified scheme of a BIG/GT system. This system includes a bagasse gasifier, equipment that transforms the bagasse into a low calorific value gas through high temperature conversion processes. This fuel gas contains particulates, tar, alkaline metals and other compounds that could affect the gas turbine operation. Thus, before introducing the fuel gas into the turbine combustion chamber, it needs to pass through a cleaning filter. The gas turbine exhaust gases have a temperature of approximately 500 °C and they still can constitute a source of heat for steam generation in a recuperative boiler, and that could be used in a cycle with steam turbines. So, in the gas/steam combined cycle there is: a topping section with a gas turbine Brayton cycle (I), and a bottoming section, that uses the heat rejected by the Brayton cycle as its source, constituted by a Rankine cycle with a steam turbine (II). This “in cascade” use (conversion) of the heat makes the efficiency of this combined cycle higher than the one of steam conventional cycles.

When process steam is needed, an extraction from the steam turbine is enough. So, there would be a BIG/GT system with cogeneration.

During gasification, the main goal is the conversion of the biomass into fuel gas through its partial oxidation at high temperatures. This gas, known as poor gas or producer gas, is an intermediate energetic, and it will be able to be further employed on another conversion process in order to generate heat or mechanical power, fitting itself to systems where the solid biomass cannot be used. Basically, the average content of the combustible components in the gas resulting from biomass is: CO between 10 and 15%, H2 between 15 and 20% and CH4 between 3 and 5%.

 

 

 

 

 

 

 

 

 

 
Figure 1 – Simplified scheme of a BIG/GT system.

 The fluidized bed gasifiers are considered to be more convenient for high capacity application in BIG/GT systems because of their high flexibility regarding the fuel (the utilization of low density fuels with fine granulometry is allowed, which is the case of most agro-industrial residues), and also due to the facility in using the data obtained in pilot plants for the designing of equipment on an industrial scale. The pressurized systems allow the disposition of more compact installations, even though the biomass feeding system is more complex.

            The BIG/GT technology has not been implemented in sugar mills yet. Several simulations have been carried out by different authors, and in Australia and in Brazil, the construction of a 3-5 MWe power pilot plant was cogitated in order to help this technology to reach its commercial stage. An interesting progress was the accomplishment of bagasse gasification tests carried out by TPS as part of the project "BRA/96/G31 Biomass power generation: sugarcane bagasse and trash" that was carried out by the Centro de Tecnologia COPERSUCAR.

Hobson and Dixon (1998) carried out a study on the possibility of implementing BIG/GT systems under Australian conditions. The thermal scheme that was analyzed is shown in Figure 2. The main conclusions of this modeling were: ·          For a steam specific consumption of 520 kg/tc (52 % of steam on sugar cane) the turbine exhaust gas energy is not enough to generate the process steam. For this level of steam consumption, 70 % of the bagasse must be by-passed from the gasifier and feed directly to the steam generators;
·         
A steam consumption reduction from 520 kg/tc to 400 kg/tc increases the BIG/GT system available power from 88 to 148 MW. An extra steam consumption reduction down to 320 kg/tc leads to a little power increase: 153 MW. For the same conditions a conventional steam system increases the available power from 37 to 43 MW (Figure 3);
·         
The annual generation efficiency using BIG/GT technology with the utilization of sugar cane trash (37 %) is almost 4 times higher than when the best technology available today is used. 

Turn (1998) presents the results of a study considering the integration of a BIG/GT system to the Okelele Sugar Company mill in Hawaii with a 120 tc/h milling capacity and a steam consumption of 420 kg/tc. The gas turbine net power is 18.8 MWe corresponding to 4.5 MWe to the steam cycle of 41 bar of pressure. During the off-season period the BIG/GT system operates as a 25.4 MWe power plant and with 28.5 % efficiency using an auxiliary fuel.

Another study considers the utilization of Steam Injected Gas Turbines, STIG, and it was accomplished by using the technical data from the Monimusk sugar mill located in Jamaica (Larson et al., 1987). As a result, a 220 kWh/tc surplus electricity generation potential was obtained for a process steam consumption reduction up-to 300 kg/tc.           

Figure 2 – Scheme of a BIG/CC system coupled to a sugar mill thermal scheme (Hobson and Dixon, 1998).

 

 Figure 3 - Simulation results of the implementation of a BIG/CC system in an Australian plant of 600 t/h capacity (Hobson and Dixon, 1998).

 References: 

Granastein, D. L., “Case Study on Waste- Fuelled Gasification Project Greve in Chianti- Italy.” Natural Resources Canada/ CANMET Energy Technology Centre (CETC), 2003.
Beenackers, A. A. C. M., Maniatis, K., Gasification Technologies for Heat and Power from Biomassa. Biomass for Energy and the Environment. Proceeding of the 9 th European Bioenergy conference. Volume 1. Pergamon., 1996.

Hobson, P. A., Dixon, T. F., “Gasification Technology – prospects for large-scale high-efficiency cogeneration in the Australian Sugar Industry”, Proceedings of the Australian Society of Sugar Cane Technologists, Vol 20, pp. 1-9, 1998.
Larson, E. D., Ogden, J. M., Williams, R. H., “Steam Injected Gas-Turbine Cogeneration for the Sugar Cane Industry”, PU/CEES Report No. 217, 1987.

Ogden, J.M., Hochgreb, S., Hylton, M.G., “Steam economy and cogeneration in cane sugar factories”, International Sugar Journal, Vol. 92, No. 1033, pp. 131-140, 1990.

Turn, S., “Biomass Integrated Gasifier Combined Cycle Technology: Status of Commercial Development Efforts and Application in the cane Sugar Industry”, Report to the BEST Project, Winrock International Institute for Agricultural Development, 1998.
USAID, 1989, “Power to the grid from sugarcane residues”, Bioenergy Systems Report. 

3- Objectives
General:
To design, built-up and extensively test a 3 MWe BIG/GT bagasse fueled power plant in a sugar mill for the evaluation and improvement of the technological drawbacks of this technology at industrial scale. 

Specific objectives: 
-         To evaluate a fluidized bed industrial gasifier (mainly feeding system, efficiency and gas cleaning).
-         To evaluate the operation of a gas turbine adapted for low calorific gas utilization (possibly using catalytic
             combustion).
-         To establish the BIG/GT system real operational achievable efficiency and the potential for improvement.
-         To find, evaluate and solve the main operational problems of the system.
-         To calculate the BIG-GT system economic indicators. 

4- Justification 

The necessity of a first industrial pilot scale test facility to progress the further commercial implementation of this technology.

The relatively high cost of the first industrial prototype makes international funding and collaboration necessary.

High efficiency electricity generation is extremely important in the actual context of a diversified food and energy producing sugar industry,

Among future ISBUC members there are research collectives with expertise in bagasse gasification and BIG/GT system modeling. 

5- Methodology and action plan 

  1. Modeling and thermodynamic optimization of a few scheme alternatives for a BIG/GT 3 MWe industrial power plant.
  2. Economic and financial evaluation of the project.
  3. Site definition for the power plant built-up.
  4. Contacts with the main equipment producers for price quotations and final definition of parameters,
  5. Revision of modeling and economic evaluation of the project proposal considering real equipment manufacturers data.
  6. Equipment acquisition and transport.
  7. Pilot plant built-up.
  8. Instrumentation and control system built-up.
  9. Pilot plant commissioning and operational problems solution.
  10. Pilot plant extensive tests.
  11. Report elaboration.
  12. International seminar for results presentation and discussion.

6- Public Target

  1. Research centers
  2. Sugar and alcohol mills
  3. Universities
  4. Governments

7- Description of the technical proposal. 

Simulation of a BIG/GT system using Thermoflex 

            A BIG/GT system consists of the combined operation of a biomass gasifier with a gas turbine. The biogas generated in the gasifier is the fuel of the gas turbine. The simulated case shows a combined cycle that generates a net power of 3 MW. 

Boundary conditions 

            The ambient air is in ISO conditions (pressure of 101,325 kPa; dry bulb temperature of 15 °C and 60% of Relative Humidity), which results in a wet bulb temperature of 10.82 °C. That is the reason why it is considered that the make-up water in the ambient is found at a temperature close to the temperature of the air wet bulb, that is, 11 °C. The considered biomass is sugarcane bagasse, which is fed into the gasifier at a temperature of 14 °C. The considered sugarcane bagasse has the following composition: 49.6% of Moisture, 1.79% of Ash, 23.58% of Carbon, 3.02% of Hydrogen, 0.1% of Nitrogen, 0.17% of Sulfur and 21.74% of Oxygen.  

Gas Turbine Modeling 

            The gas turbine to be modeled is a turbine equivalent to the Alstom GT 5, whose design characteristics or parameters are: 15 kg/s of air, 12.2 of Pressure Relation, rotation of 14000 rpm, turbine inlet temperature of 950 °C, 27.3 % electric efficiency and nominal power of 2726 kWe. As the GT 5 is designed to operate with natural gas, whose low calorific value is nearly 50 MJ/kg, the modeling considers that only the GT 5 combustion chamber will be modified in order to burn a gas of low calorific value such as the biogas generated in the biomass gasifier, whose low calorific value does not reach 8 MJ/kg. The same design parameters of the GT 5 will be maintained for the compressor, the turbine and for the electric generator. 

System Description

Operation Scheme and Parameters 

            Figure 4 shows the main screen of Thermoflex, where it is possible to see the scheme used for simulating the BIG/GT system. The gasifier generates gas at 700 °C. The gas is cooled in four stages until it gets into the scrubber at 142 °C, from where it leaves at a temperature of 40 °C and afterwards it is compressed towards the combustion chamber of the gas turbine. The compression is carried out in two stages with intermediate cooling. The heat rejected during the cooling of the gas is used along the four stages, through four heat exchangers to: (1) generate saturated steam; (2) pre-heat the air that will go to the gasifier; (3) pre-heat the gas before it gets into the combustion chamber of the gas turbine; and (4) pre-heat the feed water of the recuperation boiler. The heat rejected in the intermediate cooling of the gas compression is also used for pre-heating the feed water of the recuperation boiler. The recuperation boiler is formed by an economizer, an evaporator and a superheater. The deaerator lies between the economizer and the evaporator. A part of the feed water goes through the economizer of the recuperation boiler and the other part goes directly to the deaerator after it is pre-heated with the heat rejected by the biogas cooling. The deaerator and the economizer operate at 5 bar. 

Figure 4: Scheme Used for the Simulation of a BIG-GT System in the Thermoflex software

The superheated steam gets into the steam turbine at a temperature of 420 °C and a pressure of 25 bar. The steam for the deaerator comes from a controlled extraction at 5 bar in the steam turbine. The pressure in the condenser is 4.24 kPa. At the condenser outlet, a circulation pump pumps the condensate to the reposition water reservoir that is at atmospheric pressure. At the reposition water reservoir, there is a low pressure pump. The high pressure pump is at the outlet of the deaerator. The heat removed in the condenser is dissipated in a cooling tower. The exhaustion gases leave the gas turbine at 448 °C. At the outlet of the recuperation boiler economizer, the exhaustion gases leave at 226 °C and go to the sugarcane bagasse dryer that is at the gasifier inlet.

Consumption, Energy Balance and Performance           

The system consumes 1.063 kg/s of sugarcane bagasse. The reposition water is 1.061 kg/s due to the evaporation in the cooling tower and in the deaerator, and also due to the drain in the recuperation boiler evaporator.

The gas turbine generator produces 2611 kW and the steam turbine generator produces 1125 kW, totaling 3736 gross kW. The gross efficiency of the system is 45.26%. Because of consumption of the auxiliary equipment (pumps, fans and compressors), the net power of the system is 3000 kW, which results in a net efficiency of 36.35 %.  

Economic assessment of the system
 
Table 1. Investments and electric power generation BIG-GT cycles (in commercial stage)

Installation Cost (US$/kW)

950-1100

Efficiency

36%

Specific Cost of the BIG - GT Cycle (US$/kW)

2500

 Below some real BIG-GT power plant costs: 

VARNAMO Plant in Sweden: (source: Beenackers e Maniatis, 1996)
                                     Electric Power: 6,3 MW.

                                     Investment cost: € 35 106
                                                
Specific investment: 7936,00 US$/kW 

ARBRE Plant in England: (source: Beenackers e Maniatis, 1996)
                                     Electric Power: 10 MW

                                     Investment cost: € 35,276 106
                                                
Specific investment: 5025,00 US$/kW 

GREVE IN CHIANTI Plant in Italy : (source: Granastein , 2003) – IEA - TASK 36                                        
                                    Electric Power:
                                    Investment cost: 20M£ original configuration
                                    9,7 M£ - increase for a se4cond boiler and gas cleaning system
                                    Specific investment: 4666US$/kW 

SIGAME Project in Brazil (non executed project)
                                    Electric Power: 32 MW
                                    Investment cost US$ 110. 106
                                    Specific Investment cost: 3437,00 US$/kW

Based on these data we could assume an specific investment cost of 5000,00 US$/kW for the 3 MW BIG-GT pilot plant. Additional resources are asked for additional measuring and control technology regarding the system thermal tests. Using, real cost data and a power to cost relation coefficient of 0,6 the 3 MW BIG-GT power plant cost must be between 24 and 32 million dollars. Lower values corresponding to the ARBRE plant are must recent.

Table 2. Results of the economic calculations for the cost of the energy generated by the BIG - GT 3 MW cycle

BIG - GT Technology - 3 MW

 

Type of Biomass

LHV

(MJ/kg)

Capacity factor

Biomass Cost

($/ton)

Generated Energy Cost

(US$/MWh)

 

Sugarcane Bagasse

17.3

75%

0

218.05

 

10

223.09

 

20

228.13

 

 

Figure 5. Cost of Generated Energy for the BIG - GT Technology - 3 MW – for different biomass costs

8- Expected results 

Technical reports about the project stages related in point 5. 

9- Project budget. 

Pilot plant including built up and commissioning (gasifier, gas turbine, recuperative boiler, steam turbine, heat exchangers and BOP):                                                        US$ 15 106
Pilot plant preliminary and construction project:                   US$ 2,0 106
Additional instrumentation and control systems:                   US$ 1. 106
Project team salaries:                                                          US$ 2.106
Equipment insurance:                                                          US$ 1. 106
Manufacturers consultancies and support:                            US$¨1 . 106
International seminar for results presentation and discussion: US$ 0,5.106
Travel and dairies expenditure (including insurance):             US$ 1,5.106
P Process contingency (6,2 %):                                           US$ 0,93 106.
Project contingency (14,4 %):                                             US$ 2,61 106

Total:                                                                                US$ 27,54. 10 6

              GO TOP